Owens Corning had a water line break that connects to a main line under Kindlberger Rd on Fri, May 15. The top of the roadway was removed yesterday exposing the piping and they have located the actual leak.
BPU will also be replacing a section of the main and three valves so there will be a water outage to some customers on Kindleberger for 4 – 6 hours today, Tuesday, May 19.
Owens Corning partially back-filled the “canyon” in the road yesterday to allow work on the pipe replacement which will be done today along with most of the back filling and compaction.
Owens Corning and BPU anticipates the road reopening around May 26th if everything goes well. The detour will continue putting a lot of traffic pressure on Sunshine Road and Fiberglass Road.