The SB I-635 exit ramp to SB K-5 and NB K-5 entrance ramp to SB I-635 will close on Wednesday, March 16 and remain closed until the project is completed in mid-December 2022.
KDOT will be re-decking the NB I-635 bridge that goes over NB K-5 and the SB I-635 bridge that goes to SB K-5. This project began in October and is resuming after a break for winter.
Currently, preparations are being made for project work to start, weather permitting.
The SB I-635 exit ramp to SB K-5 and NB K-5 entrance ramp to SB I-635 will close on Wednesday, March 16 and remain closed until the project is completed in mid-December and there will be varied daily lane closures on I-635. Detours will be marked.
Two lanes of traffic along NB I-635 will be maintained during the construction. One NB lane will be moved over to the SB side of the interstate in what is termed a “contraflow lane.” SB I-635 traffic will be shifted over to allow for this. Two SB I-635 lanes of traffic will also be maintained during construction.
Please keep this in mind as you navigate around this area.